02/11/2009
|
V8 Works - Week 3 Nov 2 to 7
Week Three (2 to 7 November) Works Update
Works associated with the temporary overlay for the event continue.
Week 3 works will include:
Concrete Barriers & Debris Fences
- Continue installation along Kevin Coombes Ave and Australia Ave
- Continue debris fence installation as per above;
- Commence barrier installation along Dawn Fraser Ave (west of Olympic Boulevard).
Pedestrian Bridges
- Complete span erection of Pedestrian Bridges 1 (Australia Avenue/New England Avenue) & 3 (Edwin Flack Avenue);
- Commence stair erection of Pedestrian Bridge 2 (Kevin Coombes Avenue/Olympic Boulevard);
- Commence stair erection on Pedestrian Bridge 4 (Dawn Fraser Avenue/Olympic Boulevard);
- Commence footings for Pedestrian Bridges 5 & 6 (Showground Road);
- Commence footings for Pedestrian Bridge 7 (Australia Avenue)
Grandstands & Platforms
- Commence platform build (grandstand and corporate) along Dawn Fraser Avenue;
- Commence corporate structure at intersection of Olympic Boulevard and Edwin
- Flack Avenue;
- Commence erection of steel frame for pit building structure on Australia Avenue.
At all times and traffic management wardens will be in place to ensure the smooth passage of traffic.
The current V8 event newsletter can be downloaded below.
Please call Chris Bastic, Homebush Motor Racing Authority General Manager Stakeholder Relations, on 0418 771 552 should you have any enquiries on the temporary overlay works or other matters associated with the V8 SuperCars motor race.